This paper, presented by SAIC (the City?s program manager) provides key insight into the establishment of a mitigation bank and then the process of creating the constructed wetlands. Then the paper discusses the permitting challenges for this and for similar projects, comparing the original timeline estimates to actual permitting timelines and the overall project impact. The paper also discusses some of the typical permitting hurdles that the project has encountered.