This paper descries the effort to bring the Tampa Bay desalination plant online applying for more than 22 permits for construction and subsequent operations. In addition to this regulatory oversight, a cumulative impact analysis, several predictive modeling projects, and 6 independent assessments of pilot plant operations were undertaken to provide assurance that adverse environmental impacts were not anticipated.
Concentrate Disposal – Meeting Regulations and Keeping the Manatees Happy
| Details | |
|---|---|
| First Name | Christine |
| Last Name | Owen |
| Keywords | Tampa Bay Desalination facility, concentrate disposal, permitting |
| Year | 08 |
| File | W-4A-2_ChristineOwen.pdf |